This e-article uniquely addresses practical aspects of radon mitigation design and construction in a custom home plan.*
Please note well that this e-article is also published hereunder in among the
home foundation articles.
In this home designer's opinion, if there were other places to cite this
work within the website, he would.
SETTING THE STAGE
Before The Architect (BTA) was chosen recently to develop a custom
home plan, including a radon mitigation plan, for a to-be-built in Knoxville,
TN. **
The building authority having jurisdiction in Knox County, TN (and other
such authorities across our fruited plain) requires that new home construction
includes radon mitigation materials and methods. Know County building
authorities enforce the 2006 International Residential Code (IRC), which
includes "Appendix F, Radon Control Methods," a thin and reedy presentation in
this home designer’s opinion.
Application of both thick layers of spirit and thin layers of letter of
the IRC’s Appendix F must be tailored to a given custom home plan;
however, several matters of radon mitigation can resonate with most any plans of
custom home design and custom home building.
| Dealing with sub-slab-on-ground, constructed obstacles | |
| Arranging and preparing slab-on-ground substrates | |
| Relieving sub-slab-on-ground pressure | |
| Protecting sub-slab-on-ground radon pipe from substrate insults of silt and fines | |
| Working across changing elevations of slab-on-ground | |
| Sealing against gas leaks | |
| Siting and running radon pipe risers | |
| Identifying radon pipe risers | |
| Wiring radon mitigation systems | |
| Terminating radon pipe risers to atmosphere |
Let's radon mitigate in design and construct from the ground up. (This e-article does not recap code; the referenced code is barely over 2 pages of text and is presented well for as far as it develops the subject, which isn’t very far in this home designer’s opinion.)
DEALING WITH SUB-SLAB OBSTACLES
BACKGROUND
This is where BTA's radon mitigation plan gets mostly done in materials and labor.
BTA takes sub-slab-on-grade, substrate preparation, and slab-on-grade support seriously, in unique, home building detail. Please bear witness in this section of the website to the 20+ entries in Articles>Home Foundations.
This custom home design involves a lowest level L0 of 4406SF, of which –
| 428SF are open to atmosphere and covered, | |
| 600SF are simply open to atmosphere, and | |
| 3380SF are habitable. |
It's the habitable L0 to which a Radon Mitigation Plan directly attends; though, perimeter drains, including those bordering habitable, play a supporting role described subsequently. (Notably, there is a vehicle garage at L1 elevation, too, which slab-on-grade is separately radon gas-mitigated.)
Other custom home plan designs precede a Radon Mitigation Plan, most importantly including –
| Floor Plans for each habitable level (this custom home design has three such levels), in order to get a grip on load paths through to foundation elements, particularly interior to the perimeter | |
| A Foundation Plan, in order to define what bounds and otherwise limits the flow of radon gas in the sub-slab-on-ground gas-permeable layer, which layer should be continuous. |
FOREGROUND
In most radon mitigation plan design, sub-slab-on-ground application should
be simplified by a single, uninterrupted layer of code-conforming gas-permeable
material; however, this is not possible with almost any of BTA'S custom home
plans.
BTA's custom home design foundation plans usually engage a honeycomb-like arrangement of grade beams and modified (lesser-sized) grade beams and, occasionally, reinforced concrete strip foundations within perimeter walls and strip footings, in order to bear interior loads and support expanses of reinforced concrete slab-on-ground, particularly at contraction joints, as in this bird's eye view of the major elements to the foundation plan in this article:
| T-wall over strip footings at perimeter and major interior bearings | |
| Grade beams at lesser interior lines of bearing | |
| Lighter beams – modified grade bears – at otherwise unsupported contraction, or control, joints |
Elements of Both Foundation Plan and Radon Plan to Express Grid Patterns, Annotated, Plan View, Scaled
Crisscrossing foundation elements could, unamended by further home foundation design, create pockets of unrelieved, hydrostatic pressure to rise here and there through the slab-on-ground – areas boxed in by grade beams and interior stem wall.
| This custom home designer commonly releases such potential pressure by designing-in a continuous, moisture-permeable layer of gravel that runs in its order of vertical sequence of preparatory substrates under both slab-on-ground and beams and footings, and, thenceforth, to perimeter footing drains. | |
| Radon gas mitigation fouls this idea: a layer of gravel for gas-permeability or a pipe run underneath perimeter-interior foundation elements begs for condensate-borne or ground water-borne gas pressure locks at low points of gravel or pipe inflection, thereby disallowing free movement of sub-slab-on-ground radon gas. |
So, BTA has altered its sub-slab-on-ground layering design methodology to pierce the perimeter-interior elements at the same level with pipes as sleeves, while holding those pipes' termini within the code-conforming gas-permeable gravel layer.
Comment: This same-level design for permeability is intended to be effective for both radon gas up and out along with pipe condensate and sub-slab-on-ground moisture down and out. A two-fer.
ARRANGING SUBSTRATES
First, the substrates as section in elevation, scaled –
Radon Mitigation System Substrates to Slab-On-Grade, Section in Elevation, Scaled

In the Radon Plan for this custom home plan set, each letter is keyed to specifics – some extensively described - of materials and methods involving –
A. Slab
B. Fine aggregate
C. Moisture and gas impermeable membrane
D. Sand
E. Radon code-conforming gravel sandwiched between a certain type of geotextile fabric; this is the gas-permeable (and moisture-permeable) layer
F. Earth
G. Contraction, or control, joint
H. Expansion, or isolation, joint
I. Stem wall or beam side of face
RELIEVING SUB-SLAB-ON-GROUND PRESSURES
Now the question: how to relieve both gas and moisture pressure throughout the foundation interior of habitable?
The answer: Smooth, Schedule 40 PVC sleeves through interior beams and stem walls on about 10 linear feet centers overall, whereby the sleeves are wrapped in a specific geotextile fabric at each end and are set at midline to the gas-permeable layer.
In an abundance of caution, BTA and clients both preferred –
| 4 linear inch diameter pipe sleeves – larger of conforming sizes | |
| 6 linear inch thick gas-permeable (and moisture-permeable) layer – in lieu of 4 linear inches, principally in order to give a little wiggle-room to the pipe sleeves and (specifically to the BTA foundation plan) to permit centerline passage through modified grade beams (12 linear inches square). |
In plan view, this is how BTA expressed sleeve passages (left to right, through grade beam, stem wall, modified grade beam) –
Pressure Relief Sleeves in Radon Mitigation Plan, Plan View, Scaled

Comment: Concern over weakening structure with pressure relief sleeve passages would be, in BTA's opinion, overdone: the lightest reinforcement of this foundation element's passage will be through the modified grade beams at 12 linear inches square, 3500 psi concrete extensively prescribed and proscribed, with 3-Grade 50 #5 deformed rebars continuous top and bottom under not more 3 linear inches cover and not less than maximum aggregate diameter plus ¾ linear inch and crossing bars top and bottom on 16 linear inch centers similarly covered.
WORKING ACROSS CHANGING ELEVATIONS
Two occasions arise in this custom home plan whereat pressure relief levels change elevation at L0 –
| Between so-called finished habitable and a rough-finished workshop the full depth of L0, which workshop's slab-on-grade floor is set not less than 6 linear inches below finished slab-on-ground, in order to let for a gas curb, and slopes overall to a vehicle door at perimeter by 1/8 linear:1 linear foot | |
| Between slab-on-grade at perimeter stem walls and exterior, perimeter footing drain (note that BTA's draining both sub-slab-on-ground hydrostatic pressure and radon pipe condensate, while at the same time providing positive air pressure from atmosphere upwards through the radon mitigation system, since the perimeter footing drains exhaust to light). |
In both occasions of such change in elevation, contractors are guided to apply smooth Schedule 40 PVC fittings through foundation elements –
| To adjust to centerlining the sleeves to the permeable layers on the interior | |
| To adjust a centerlined interior permeable layer sleeve to an intersection with the perimeter footing drainpipe on the exterior |
A WHOLE LOT OF SEALING GOING ON
| Pipe sleeves are sealed to silt and fines at termini with a certain type of geotextile fabric | |
| Through-foundation and through-slab-on-ground pipes and other materials insinuations are sealed with "polyurethane caulk or equivalent" | |
| Gas-permeable (and water-permeable) gravel layer is sealed continuously top and bottom to silt and fines | |
| Soil gas intrusion to habitable is retarded with a continuous layer of InsulTarp at .002 PERM | |
| Both contraction, or control, joints and expansion, or isolation joints are sealed with elastomerics, noting that the latter are also sealed by lap-up of the moisture- and gas-impermeable membrane and backerrod. |
SITING RADON PIPE RISERS
Three considerations –
How many radon pipes shall rise to atmosphere?
"Typically, one collection point is needed for every 65 m2." Source: footnoted article by C. P. Connell.
Quote the client who wrote it better than could the author: "So that means a
collection
point for every 700SF of slab-on-ground. The basement is
about 3000SF, implying . . . 5 collection points. I don't suppose each
collection point has to have its own stack [2006 IRC, "Appendix F" is
herewith inexplicably moot]. . . Now, to put it in context, he is talking about
remediation. The 700SF is related to how well the sub-slab-on-ground
‘communicates'. Our gravel base should give good sub-slab-on-ground
communication and thus extend the ‘pressure field' beyond 700sqft. However, I
don't know what kind of sub-slab-on-ground environment the author is typically
working with when he says that a collection point is typically need for every
700SF.
Additionally, the current design incorporates a continuous sub-slab-on-ground
barrier. Do most of the author's remediation projects have such a
barrier? [Doubtful.] Nevertheless, this is the only article I've seen that
actually gives any collection point/SF and we would be foolish to ignore this
data point."
This designer agreed for L0 (noting
that the garage in this custom home plan passages to L1, whereat, another radon
mitigation system is designed for construction, thereby, there'll be more).
Where to set the radon mitigation
pipe risers through the slab-on-ground?
Reckon
that the radon pipes should be more or less evenly distributed across the vented
slab-on-grade, and may, to code (and, in this custom home designer's opinion and
in the client's, should always) be required to extend past the roof deck
–
How to tell the contractors where the pipes pierce the slab-on-ground?
Same way this custom house
designer tells ‘em where to site the sanitary DWV stubs – dimension statements,
right on the drawn sheet – referencing strip foot corners (dark hatches
designate pilasters atop strip footings, little squares are anchor bolts,
intersecting member is a grade beam).
Radon Pipe Siting through Slab-On-Grade, Plan
View, Scaled (the DWV "WET A" site is dimensioned on the Foundation Plan, of
which this excerpt from the Radon Plan is a stripped-down version)
Comment: Temporarily seal radon pipe stubs from leftovers to a messy placement, just as with DWV stubs.
UP, UP, AND AWAY – IDENTIFYING RADON PIPES
As radon mitigation pipes rise through the home, and aside from limitation on length of horizontal runs (see above) –
This note appears on the Radon
Plan sheet, directed at a radon riser pipe symbol (4 linear inch diameter
circle, x'ed on the interior and annotated "Rn") - LABEL STUB "RADON
REDUCTION SYSTEM" (EVERY PIPE, EVERY LEVEL INCLUDING ATTIC) AND TEMPORARILY
SEAL TO FOULING, TYP (EVERY PIPE, EVERY LEVEL INCLUDING ATTIC)
| |||
| Keep vertical runs interior to perimeters – it'll minimize condensate | |||
| Thermally insulate attic pipes (and surfaced garage pipe where a radon mitigation system separate from others is involved) | |||
| Join pipes with colored dope – to be sure of what's sealed |
WIRING RADON MITIGATION SYSTEMS FOR IN-LINE FANS
The code's reference to power source herewith is amplified as follows –
| Expect that each radon riser will have its own in-line fan | |
| Securely set a j-box at 4 linear feet over attic floor level and within 2 linear feet of each pipe | |
| Supply with 120V/20A dedicated circuit wired preferably to each standalone or, less preferably, in parallel | |
| Apply only THHN conductors in rigid or flexible conduit, not NM-B or similar | |
| Provide temporary, physical lock-out for overcurrent protection | |
| Provide pilot light switch(es) on readily visible and accessible, in-habitable wall surface |
* For further perspective, please consider searching ‘truth about radon' and the likes generally and, among others, specifically, http://www.forensic-applications.com/radon/radon.html for "Radon – A Brief Discussion" by Caoimhín P. Connell, Forensic Industrial Hygienist
** Note please that the author knows of no other home radon mitigation plan as broadly and deeply prosecuted and presented as the one done by BTA for the Knoxville custom house plan.
About Us ◊ jrp2h2000@yahoo.com ◊ 770-889-6964 ◊ Site Map
· · · · · · ·
(If this is your first visit to Before The Architect, please consider spending a few moments looking over the Site Map, in order to get a feel for the website design. Before The Architect E-mail: jrp2h2000@yahoo.com.)